One small change on a drawing: what the Hyatt Regency collapse teaches about revision control

In 1981 a change to a hanger rod detail, never formally reviewed, doubled the load on a walkway connection in a Kansas City hotel and killed 114 people. The same kind of drift between drawings and site still happens on projects today.

Navy banner reading “One small change on a drawing: what the Hyatt Regency collapse teaches about revision control”, beside a simple engineering drawing with an amber revision cloud.

On the evening of 17 July 1981, between 1,500 and 2,000 people gathered in the atrium of the Hyatt Regency hotel in Kansas City for a tea dance. Above them, two suspended walkways crossed the atrium, one hanging directly below the other. At about 7:05 pm, the upper walkway’s connections gave way, and both walkways fell onto the crowd. 114 people died and more than 180 were injured.

Investigators did not blame poor workmanship or bad materials. The cause sat in the documents.

What changed, and how

The original design

The design drawings showed each walkway hanging from the roof on long steel hanger rods. A single continuous rod passed through the fourth-floor walkway and carried on down to support the second-floor walkway below it. The nut under the fourth-floor beam only had to carry the fourth-floor walkway.

The change

During fabrication, the steel fabricator proposed replacing each single long rod with two shorter, offset rods: one from the roof to the fourth floor, and a second from the fourth floor down to the second. It was easier to make and install.

On paper the change looked minor. In practice, the fourth-floor beam connection now carried both walkways. The load on that connection roughly doubled.

Diagram comparing the original walkway design, where one continuous rod meant the upper connection carried one walkway, with the as-built design, where two offset rods made the upper connection carry two walkways.
As designed, the upper connection carried one walkway. As built, it carried two. Simplified diagram, not to scale. Sources: STRUCTURE magazine, 2016; National Bureau of Standards, 1982. View full size (opens in a new tab)

How it slipped through

According to the account in STRUCTURE magazine:

  • The project manager gave conditional approval, but the structural engineering manager asked for a formal change request. The fabricator never submitted one.
  • The original project engineer and senior designer had left the job early, so the reasoning behind the original detail was not passed on.
  • Incomplete shop drawings went to an outside detailer, who assumed the connection had already been designed.
  • A technician raised a question about the rods, and it was answered from memory rather than checked.

The National Bureau of Standards found that the connection did not meet the steel design code of the time. Damages to victims and families passed US$100 million, and the engineer of record and project manager lost their licences.

Why this still matters

Hardly any project goes from the first drawing to handover without changes. Fabricators suggest easier details. Site teams find clashes. Clients move walls. Each change creates a new revision, and each revision has to reach every person working from the old one.

The risk is not the change itself. The risk is the gap between the drawing someone is working from and the drawing that is actually approved.

Ghana is in a period of heavy building. The government describes its Big Push roads programme as a US$10 billion investment over five years, and there is new work in refining, power and solar. More projects mean more drawings, more subcontractors and more chances for a revision to get lost.

Common ways documents drift

  • A superseded drawing is still pinned up in the site office.
  • A fabricator works from a shop drawing that was never checked against the design.
  • A change is agreed by phone or in a meeting, and never written into a revision.
  • A method statement is written for the original design, not the revised one.
  • QA/QC records refer to a drawing number with no revision letter, so nobody can tell which version was inspected.

What to do about it

Five-step flow: change proposed, engineer reviews, revision issued, site acknowledges, records name the revision. The engineer review step is highlighted as the one skipped at the Hyatt Regency.
Every design change should pass all five steps, in writing. At the Hyatt Regency, the engineering review was skipped. Source: STRUCTURE magazine, 2016. View full size (opens in a new tab)

Keep one register

  • Hold a single drawing register for the project, listing every drawing, its current revision and its status (for information, for construction, superseded).
  • Mark superseded copies clearly, or remove them from site.

Treat every change as a design question

  • Route every proposed change, even a “simple” one, through the engineer responsible for that element.
  • Ask what the change does to loads, connections and anything else it touches. In 1981, a change in how the rods were arranged changed how the load travelled.
  • Record the decision in writing before work starts.

Close the loop with the site

  • Issue new revisions with a transmittal that each recipient acknowledges.
  • Brief the crew when a revision changes how they will build something.
  • Update the method statement and inspection test plan at the same time as the drawing.

Make records point to revisions

  • Every inspection record, permit and QA/QC sign-off should name the drawing and its revision.
  • At handover, it should be possible to show which revision was built and who checked it.

Plan for people leaving

  • When an engineer or supervisor leaves a project, a short written handover of open questions and design intent avoids the gap that hurt the Hyatt project.

Key points

  • The Hyatt Regency walkways fell because a detail changed and the change was never properly reviewed.
  • The documents existed. What broke was the link between the change, the engineer and the people building it.
  • Revision control is not paperwork for its own sake. It is how a site knows it is building what was designed.

The drawings on a project are a set of decisions. When the decision changes, every copy of the drawing has to change with it.